|
When there has been no study or
assessment of the possible impacts or viability of the proposed
embankment, the question thrown by Jairam against himself is, on which
basis his ministry gave the forest clearance in July 2010?
During the debate on March 4, 2011 the minister also informed the
Parliament that “the final stage-II forest clearance for the Polavaram
Project was given way back in July, 2010” and never mentioned about
non-compliance of FRA (Forest Rights Act) while giving the clearance.
The minister seemed to be misleading the Parliament here.
It has been brought to the attention of the Minister by
water management
expert Himanshu Thakkar that the forest clearance was
given by the MoEF in July 2010 without settling issues related to the
Rights of dwellers living in the affected villages as required under the
FRA. Gram Sabha resolutions to that
effect from seven villages to be affected by proposed forest diversion
for the Polavaram project have been sent to the Minister and also to the
members of the statutory Forest
Advisory Committee (FAC)
constituted under the Forest Conservation Act. Similar resolutions from
additional fifteen villages have been sent from Andhra Pradesh.
Following Mr. Thakkar’s letter, Minister had responded that he would get
the issues examined. The very next day, on Nov 22, 2010, Mr Ramesh
himself wrote to the then AP CM Shri K Rosaiah saying, “the matter that
has been made available to me clearly seems to indicate that the claims
of local tribal communities do not seem to have been settled. This is a
very serious matter.”
The Minister, however, having received no response from the
AP
Chief Minister, wrote again to
the new AP CM Kiran Kumar Reddy on Jan 25, 2011 adding, “I am awaiting a
response from the state government.”
In the meantime, following a detailed representation
including gram sabha resolutions to all the FAC members, the statutory
committee in its meeting on Oct 25, 2010 (minutes are available on MEF
website) decided, “The FAC recommended that these complaints may be sent
to the Ministry of Environment & Forests to take appropriate action at
the Ministry level. The Ministry may give special consideration to the
following:
Examine the alleged FRA violations and request the State
Government to provide details on FRA compliance as per the law and
circular of Aug. 2009; Examine the issue of forest land diversion for
the embankments which are planned to prevent the submergence in
adjoining States (the
existing project report makes no
mention of forest diversion for embankment even though it requires huge
forest land and needs a special mention or, at least, an inclusion) in
the
Project proposal; Examine the
discrepancies between the facts submitted when seeking clearance from
the FAC and EAC respectively and take action if necessary.”
FAC being a statutory body, the state government has to
satisfy the committee on the issues specifically raised by it. This is
yet to happen.
Under these circumstances, the forest clearance given to the
project cannot be considered final and the minister should have brought
this issue to the notice of the upper house. Not mentioning these issues
while talking about the Forest clearance is tantamount to misleading the
house.
Here, it may also be added that the
Central Electricity Authority is
yet to give concurrence to the power component of the Polavaram project.
Such a concurrence is a statutory requirement under section 8 of
Electricity Act 2003. The CEA, in response to an RTI query has informed
SANDRP that the application of concurrence from Polavaram was returned
to the developer without any concurrence due to issues related to
hydrology and because proposed installed capacity of 960 MW is unviable.
The proposal to increase the cost of the project to Rs. 16010.45 crores
from Rs. 10151.04 crores was also not accepted by the advisory Committee
on Irrigation, Flood Control and Multi Purpose Projects in its meeting
on Oct 27 2010 following intervention by Joint Secretary (Exp), Dept of
Expenditure. A number of petitions are also pending in courts against
the project.
The Project was earlier given
funding under the Accelerated Irrigation Benefits Programme (AIBP) under
erroneous claims. The Command area of the Polavaram project also
significantly coincides with the command areas of Pushkara and Tadipudi
Lift Irrigation Schemes, both of which are also getting funds under AIBP.
CAG has already raised questions about all these. Almost all the claimed
clearances of the project seem to be raising a lot more questions on
many fronts.
Under these circumstances, when the project looks to be moving against
all laws of the land, consideration of the project by the Union
government under
National Project scheme (as stated by the minister in
Parliament) and making it eligible for 90% central funding seems to be a
more unlawful act pursued by the government itself. |